Port WHARF Crane CC05

SEABOARD have recently completed the Port crane retrofit works on the CC05.

​

The scope consisted provision of experienced & skillful workforce to carry out the following package:

 

  • Renewal of entire bolts & nuts and hydraulic torguing of 3600sets was successfully finished at 14days without delay.
     

  • Renewal of all crane manhole covers.
     

  • Provision of scaffold erection for the entire retrofit project.

 

We deployed our Technical team for entire retrofit period and successfully carried out the work and completed in 14 days without delay including supply all materials for the above works.

 

As part of SEABOARD value offering of not just delivering of the components but of committing for a turn-key solutions.

 

In essence, SEABOARD has delivered feasibility, fabrication, project management, local authority formalities logistic, installation, supervision and commissioning services.